D & R General Contracting, Inc. was awarded the 2008 Roads & Sidewalk Program. Construction is well underway and will continue throughout the summer, the majority of which is scheduled to be completed before the opening of school.
Finished pavement has been completed on Keyes Road, Munroe Place, Crest Street and West Street.
Work is well underway on Longfellow Road, Peter Buckeley Road, Paul Revere Road, Dover Street and Hemlock Drive. Finished pavement in these areas is scheduled to be completed within the next few weeks.
If you have questions or need additional information, please do not hesitate to contact Concord Public Works Engineering Division at 978-318-3210.
Munroe Place - July 22, 2008
Munroe Place - July 10, 2008
Crest Street - July 22, 2008
Crest Street, July 22, 2008
Crest Street - July 15, 2008
Keyes Road - July 22, 2008
Keyes Road - July 22, 2008
Keyes Road Reclamation - July 10, 2008
Planned Road Improvements Include:
Crest Street
Dover Street
Hemlock Lane
Keyes Road
Longfellow Road
Main Street (Monument Square to Sudbury Road)
Munroe Place
Nut Meadow Crossing
Old Road to Nine Acre Corner
Paul Revere Road
Peter Bulkeley Road
Rollingwood Lane
West Street
Planned Sidewalk Improvements Include:
Lawsbrook Road (Portions)
Lexington Road
Main Street/Sudbury Road
Old Road to Nine Acre Corner
This work will also include drainage improvements on Old Road to Nine-Acre Corner and portions of Main Street.
Click Here to view a detailed map of the Street Plan
Click Here to view a detailed map of the Sidewalk Plan