To all:
Here is the copy of the two week look-ahead schedule, as submitted by Tom Prendiville, the Superintendent for CTA Construction, Inc.
05/13/08 to 05/27/08
1. Remove and dispose of existing drywell structures, fill with compacted lifts.
2. Install and compact structural fill to sub-grades for interior slab.
3. Remove existing CB at NW corner of building foundation and associated transite piping within the building footprint.
4. Delivery of rebar (week 5/19/08).
5. Excavate for new foundation starting at the NW corner of foundation.
6. Form, install rebar at footing starting at NW corner.
7. Inspection of footings and placement of footings.
8. Install septic system leaching field.
Regards,
John Christiansen
Daedalus Projects, Inc.
Clerk of the Works at the Willard School
|