Town of Concord representatives met with project contractor, D.W. White, State regulatory and MassDOT staff along with their consultants on Thursday, December 13, 2012 to review progress on the project’s environmental permitting requirements. Submittals for the Storm Water Pollution Prevention Plan (SWPPP), onsite environmental monitor and plan, and proposed onsite wetland specialist were reviewed with favorable comments.
D. W. White has re-submitted their project schedule for review and approval by MassDOT. Approval is anticipated in the upcoming weeks and will be posted on the Town’s website upon receipt.
Project Contractor, D. W. White is currently working on installation of silt fence, hay bales and has completed construction signage. Work is also being done on asbestos abatement on the 8 houses along route 2 in Lincoln, in preparation for demolition.