Nagog Pond
Nagog Pond Intake Replacement
Project Manager
Alan Cathcart
Concord Pubic Works Director
Design Engineer
Environmental Partners
Quincy, MA
Contractor
D&C Construction
Weymouth, MA
Sign up to receive project updates
Click to subscribe to Nagog Project Updates emailing list (google group)
Project Summary
The Town of Concord (the Town) is in the process of making comprehensive improvements and upgrades to its existing surface water supply known as Nagog Pond, which has been utilized by the Town as a water supply since the early 1900s. As part of these improvements, the Town intends to replace the existing 16-inch cast iron intake pipe with a new 16‐inch inside diameter (ID) high density polyethylene (HDPE) intake pipe.
The existing intake pipe extends approximately 1,800 feet into Nagog Pond from the gatehouse at the dam and is partially supported by wooden cribbing in some areas and is covered by sediment in others. Physical inspections of the intake pipe have indicated that it has significantly deteriorated, resulting in decreased hydraulic carrying capacity and risk of failure. Due to the condition of the existing intake pipe, the Town is replacing it with a new 16‐inch ID HDPE pipe, which includes an intake structure with an intake screen and automated air burst cleaning system.
The proposed work includes two phases of construction. Based on the plan of work proposed by the selected contractor, the first phase of the project will involve deep water work which will include fusing and floating of the intake pipe along the water surface and then submerging it into position, followed by a later phase of work that will involve dewatering and limited dredging performed along a portion of the shallow pond bottom (the cove).
Updated 9/17/2020
2021 Project Updates
- Aug 13 - Nagog Project Update
- Aug 6 - Nagog Project Update
- July 26 - Nagog Project Update
- July 12 - Nagog Project Update
- July 6 - Nagog Project Update
- June 28 - Nagog Project Update
- June 18 - Nagog Project Update
- June 14 - Nagog Project Update
- June 4 - Nagog Project Update
- May 21 - Nagog Project Update
2021 Information Sessions
2020 Project Updates
- December 25 - Nagog Project Update
- December 18 - Nagog Project update
- December 11 - Nagog Project Update
- December 4 - Nagog Project Update
- November 27 - Nagog Project Update
- November 13 - Nagog Project Update
- October 23 - Nagog Project Update
- October 16 - Nagog Project Update
- October 9 - Nagog Project Update
Project Schedule
Nagog Intake Replacement Construction - Phase 1
- Construction started March 2, 2021
- Construction completion projected for May 28, 2021
Updated 4/12/21
Town of Acton - Project Liaison
John S. Mangiaratti
Town Manager
Town of Acton
Phone (978) 929-6611
manager@actonma.gov